Infrastructure Capital Works - Updated 30 April 2012

Location Reason for closure Start Anticipated Completion Project Manager
Winifred Crescent, Toorak (Cloverdale - Berenice) Asphalt Resurfacing  1 May 12 3 May 12 JB
Perth Street, Prahran (Greville St - Commercial Rd) Asphalt Resurfacing  30 Apr 12 2 May 12 JB
Beaver Street, Malvern East Road Reconstruction  24 Apr 12 30 Sep 12 JB
Toorak Avenue, Toorak (Moonga Rd - Merriwee Cres) Asphalt Resurfacing  24 Apr 12 30 April 12 JS
Short Street, Malvern East (Malvern Rd - No Thru Road) Asphalt Resurfacing  24 Apr 12 30 April 12 JS
Ferguson Street, Glen Iris (Malvern Rd - Allenby Ave) Asphalt Resurfacing  24 Apr 12 30 April 12 JS
Glenferrie Rd, Malvern - Stage 6 Streetscape Works  30 Jan 12 4 Jun 12 JB
Winter Street, Malvern Road Reconstruction  7 Nov 11 30 Apr 12 JB
Yarra River alongside Alexandra Ave & Grange Rd, Toorak Yarra River Biodiversity Project  20 Apr 11 30 Apr 12  

Council Construction Management - Supervision - Survellience Officers

James Edmond Infrastructure Coordinator JE 8290 3540
John Sherrard Construction Team Leader  JS 8290 3541
John Blatti Construction  Engineer JB 8290 3512
Katherine O'Connell Project Manager KO 8290 3555