Harold Holt Swim Centre installations

Harold Holt swim centre showing outdoor pool
The secondary boiler for the 50m pool at Harold Holt Swim Centre is at the end of it's life and needs replacement.

A new energy efficient condensing boiler will replace the existing one.

The installation will occur in May and take four days to complete. The works will not impact the pool or visitors.

A Building Management System (BMS) will also being installed. This will integrate all building operations (pool system, heating, cooling and lighting) into one system.

Installation – Building Management System

Project status Installation of a boiler and Building Management System (BMS)
Project type Installation
Construction contractor BSA Group (Vic) - Building Management System
Construction

28 February to 30 March 2021

Contact (design)

Building Project Manager

P: 8290 1333

E: brsmith@stonnington.vic.gov.au

Scope of works

Installation of a Building Management System (BMS) that forms part of Council's energy reduction program.

The BMS will integrate the pool system, heating and cooling and lighting of the swim centre into one system.

Installation of boiler

Project Replacement of end of life boiler with a high efficiency condensing boiler
Installation contractor BSA Group (Vic)
Expected installation/completion dates 19 February to 1 June 2021
Scope of works  

Procurement from the Netherlands

Demolition of existing boiler

Installation of the new boiler