Road upgrades on Carlyle Way, Malvern East

  • Project summaryWe will be reconstructing the road on Carlyle Way, between Glenbrook Avenue and Hedgeley Avenue, as part of Council’s annual road renewal program.
  • Led byCity of Stonnington
  • Project statusIn progress

Project overview

We will be reconstructing the road on Carlyle Way, between Glenbrook Avenue and Hedgeley Avenue, as part of Council’s annual road renewal program. We’ve prioritised this road for renewal because of its poor condition and to improve safety and accessibility.   

As part of these works, we will be: 

  • upgrading the road surface with new asphalt 
  • carefully removing and reinstating existing bluestone kerbs and channels  
  • replacing kerbs and vehicle crossings to improve access and safety 
  • installing new stormwater drainage to help manage rainfall.

Scope of works

Noise 
Construction activity will occur within these hours: 

  • Monday to Friday between 7 am to 4.30pm 
  • Some Saturday work, if required.

Access 

Traffic controllers will be on-site to help manage access for residents around the work area.  

During some stages of construction, driveway access in Carlyle Way will be temporarily restricted for up to 5 business days during and after concrete pours. We acknowledge these works may cause some disruption. We have contacted impacted residents directly and we will keep you informed as works approach your property. 

Bin collections 

Bin collections will continue as normal for residents. Please place your bins out on your regular collection day. 

Parking 

On days when concrete is being poured, we kindly ask residents to park on Glenbrook Avenue, Hedgeley Avenue or Ferncroft Avenue. No parking permits are required for these streets.  

Timeline

Works will be delivered from late-July 2026 and are expected to be completed by late-October 2026, weather and site conditions permitting.