Sir Zelman Cowen Park sport and recreation plan

  • Project summaryIn 2025-26 we’re developing a sport and recreation plan for Sir Zelman Cowen Park in Kooyong.
  • Led byCity of Stonnington
  • Project statusIn progress
  • Engagement statusCommunity engagement closed
  • Community consultationLearn more about the consultation

Glenferrie Rd, Kooyong 3144  View map

Google Map

Project overview

In 2025-26 we’re developing a Sport and Recreation Plan for Sir Zelman Cowen Park in Kooyong. 

The Plan will align with the Gardiners Creek (KooyongKoot) Masterplan, which was developed in consultation with the community in 2020. It seeks to enhance environmental health, improve biodiversity and support recreation along the Gardiners Creek corridor. View previous consultation on the Masterplan. The Plan will support the implementation of Zone 2 of the Gardiners Creek (KooyongKoot) Masterplan.

To meet the needs of current and future users, the new Plan will create a long-term roadmap that will guide the park’s activities and prioritise potential opportunities for investment. 

In late-2025 we invited community feedback to understand how they currently use the park, their aspirations for the future and any other feedback that will help us shape the Plan. 

What we heard will be considered with a review of Council's policies and the park’s assets, functionality, condition, usage, visitor behaviour and safety concerns to develop the final Plan. 

Once we have a draft Plan, we’ll share it for community feedback before we finalise it and begin implementation. 

Scope of works

Integration with the Gardiners Creek KooyongKoot Master Plan including:

  • sports fields, playing surfaces and drainage
  • sports lighting
  • pavilions, change rooms and toilets
  • supporting infrastructure
  • stormwater harvesting, irrigation and drainage
  • parking
  • usage
  • safety considerations
  • visitor behaviour.

Timeline

2020 Gardiners Creek (KooyongKoot) Master Plan adopted
late-2025 Community engagement on the Sport and Recreation Plan
early-2026 Draft Sport and Recreation Plan development

 

early-2026 Draft Sport and Recreation Implementation Plan
April 2026  Public Exhibition of draft Sport and Recreation Plan
mid-2026

Final Sport and Recreation Plan

mid-2026 onwards Advocate and seek funding

This project timeline is an indication only and may be subject to change.