The City of Stonnington is reconstructing Charles Street, Prahran from Commercial Road to Greville Street.
Works will include reconstruction of the existing road pavement, new footpaths, bluestone kerb and channel and new trees.
The road width will be narrowed slightly to accommodate wider footpaths and the existing trees will be replaced by new trees on both sides of the street.
These works reflect our ongoing commitment to providing the community a safe and functional road and drainage network across the city.
We recognise works of this nature may cause some inconvenience, and thank you in advance for your patience and understanding.
Remove existing road pavement, kerb and channel
Narrow road pavement to accommodate wider footpaths
New asphalt road pavement
New bluestone kerb and channel
New footpaths
Remove existing trees
Plant new trees on both sides of the street
Late-June to late-2023.
Reconstruction of Charles Street from Commercial Road to Greville Street will be delivered over four stages:
Stage 1 | site set-out
Duration | one week (approx)
Stage 2 | Commercial Road to Thomas Place
Construct new underground drainage, kerb and channel, asphalt footpath and structural soils to allow for new tree planting within the street.
Duration | 10 weeks (approx)
Stage 3 | Thomas Place to Greville Street
Duration | six weeks (approx)
Stage 4 | Asphalt pavement works and site decommissioning
Duration | 15 days (approx)
Contractor
ADP Constructions Pty Ltd Adrian Petrolo M: 0401 145 822
City of Stonnington
Kush Patel Project Manager E: kpatel@stonnington.vic.gov.au P: 8290 1333
Emergency (24 hours)
8290 1333
Footpath widening