Harold Holt Swim Centre improvements
- Project typeImprovement works
Council has adopted a masterplan for the Harold Holt Swim Centre that will deliver restoration and improvement works to this popular facility over a number of years.
The implementation of the masterplan will occur over several stages and these works, together with an ongoing maintenance program, will ensure the facility continues to meet the requirements and expectations of visitors to the centre.
Extended centre closures throughout 2020 and 2021, due to COVID-19 restrictions, provided an opportunity to fast track some planned maintenance works.
Latest News
19 October 2022 | Diving is back at Harold Holt for the first time since 2003
Future works
Project |
50-metre outdoor pool - accessible ramp |
Project |
50-metre outdoor pool surrounds and grandstand - upgrade |
Completed works
Project
|
Heritage dive tower and pool restoration
|
Status |
Completed October 2022
Reopened 19 October 2022
Harold Holt dive pool back with a splash
|
Watch the works |
|
Scope of works |
Restore the heritage dive tower (with Heritage Victoria approved modifications)
Reconstruct dive tower spiral staircase and add security gate
Restore the dive pool
Install new 1-metre and 3-metre springboards to the dive pool
Demolish existing plant store, build new store north of the dive tower and install new plant
New paving, fencing and landscaping
|
Community updates |
15 October 2021 Resident Notification(PDF, 269KB) |
Consultation |
In 2019, community consultation was completed to determine the level of support for restoring the dive tower and pool.
View Harold Holt dive tower and pool consultation
|
Photo gallery |
|
Project |
Building Management System installation |
Status |
Completed June 2021 |
Scope of works |
Install BMS system to integrate all building operations (pool system, heating, cooling, lighting) into one central control system. |
Project
|
Boiler replacement
|
Status |
Completed June 2021 |
Scope of work |
Decommission and remove boiler
Install new condenser boiler
Commission
|
Project
|
Restore 50m outdoor pool |
Status |
Complete December 2020 |
Scope of works |
Drain 50m outdoor pool
Remove all tiles
Deep clean pool shell
Retile pool
Render pool walls
Refill and prepare pool for use
|
View the works |
|
Location
1409 High Street, Glen Iris 3146 View map
-37.8584137,145.0445844
1409 High Street ,
Glen Iris 3146
1409 High Street ,
Glen Iris 3146